Currently working on Phase 4
As the project progresses, we expect the length of the phases to contract. If you check the dates of previous phases you will see the duration has been decreasing and this is expected due to increasing number of volunteers and improved technology. So check back from time to time to see how we are progressing.
| Phase | Start Date | End Date |
|---|---|---|
| Phase 1 | 1 November 2023 | 30 September 2024 |
| Phase 2 | 1 October 2024 | 27 March 2025 |
| Phase 3 | 28 March 2025 | 28 August 2025 |
| Phase 4 | 29 August 2025 | 6 December 2025 |
| Phase 5 | 7 December 2025 | 28 February 2026 |
| Phase 6 | 1 March 2026 | 6 June 2026 |
| Phase 7 | 7 June 2026 | 5 September 2026 |
| Phase 8 | 6 September 2026 | 5 December 2026 |
| Phase 9 | 6 December 2026 | 6 March 2027 |
| Phase 10 | 7 March 2027 | 5 June 2027 |
| Phase 11 | 6 June 2027 | 4 September 2027 |
| Phase 12 | 5 September 2027 | 4 December 2027 |
| Phase 13 | 5 December 2027 | 4 March 2028 |
| Phase 14 | 5 March 2028 | 3 June 2028 |
| Phase 15 | 4 June 2028 | 2 September 2028 |
| Phase 16 | 3 September 2028 | 2 December 2028 |
| Phase 17 | 3 December 2028 | 3 March 2029 |
| Phase 18 | 4 March 2029 | 2 June 2029 |
| Phase 19 | 3 June 2029 | 1 September 2029 |
| Phase 20 | 2 September 2029 | 1 December 2029 |
| Phase 21 | 2 December 2029 | 2 March 2030 |
| Phase 22 | 3 March 2030 | 1 June 2030 |
| Phase 23 | 2 June 2030 | 31 August 2030 |
| Phase 24 | 1 September 2030 | 30 November 2030 |
| Phase 25 | 1 December 2030 | 1 March 2031 |
| Phase 26 | 2 March 2031 | 31 May 2031 |
| Phase 27 | 1 June 2031 | |